Online patching is supported by the capability of storing multiple application editions in the database, and the provision of a dual application tier file system. At any given point in time, one of these file systems is designated as run (part of the running system) and the other as patch (either being patched or awaiting the start of the next patching cycle).
For applying a patch in R12.2 you need to use adop and run through all below phases in sequence mentioned below.
1) adop phase=prepare
2) adop phase=apply patches=<patch_number1>,<patch_number2> workers=<number_of_worker>
3) adop phase=finalize workers=<number_of_worker> (called automatically)
4) adop phase=cutover workers=<number_of_worker>
5) adop phase=cleanup (called automatically)
OR
Running all phases in single command:
adop phase=prepare,apply,finalize,cutover,cleanup patches=<patch_number1>,<patch_number2>
——————————————————————————————————————–
DESCRIPTION OF EACH PHASE
1) PREPARE PHASE DETAILS
Used to start a new online patching cycle
How to execute:
A) Set the environment by executing (sourcing) the run file system environment file:
$ source <EBS install base>/EBSapps.env run
B) Verify envirionment
You can confirm that the environment is properly set by examining the relevant environment variables:
$ echo $FILE_EDITION run
$ echo $TWO_TASK dbSID
C) Download Patches
Download patches to be applied and place then in the $PATCH_TOP directory of your system. This directory is pre-created by the install in the non-editioned file system (fs_ne) and should not be changed.
Important: On a multi-node system with non-shared file systems, you must copy the patch files to each separate $PATCH_TOP directory, so that the patch files are available from the same location on all nodes.
D) Unzip the patch
$ unzip <patch>.zip
E) Run Prepare Command
Prepare the system for patching by running the following command to start a new patching cycle:
$ adop phase=prepare
What it will do:
• Checks whether to perform a cleanup, which will be needed if the user failed to invoke cleanup after the cutover phase of a previous online patching cycle.
• Checks the integrity of the database data dictionary. If any corruption is found, adop exits with an error.
• Checks system configuration on each application tier node. A number of critical settings are validated to ensure that each application tier node is correctly registered, configured, and ready for patching.
• Checks for the existence of the “Online Patching In Progress” (ADZDPATCH) concurrent program. This program prevents certain predefined concurrent programs from being started, and as such needs to be active while a patching cycle is in progress (that is, while a database patch edition exists). If the ADZDPATCH program has not yet been requested to run, a request is submitted.
Note: ADZDPATCH is cancelled later on when the cutover phase is complete.
• Checks to see if the patch service has been created. adop requires that a special database service exists for the purpose of connecting to the patch edition. This service is created automatically, but its continued existence is validated on each prepare.
It can be checked by the database parameter SERVICE_NAME
SQL> show parameter service_name NAME TYPE VALUE ------------------------------------ ----------- --------------- service_names string dba, ebs_patch
Here dba is the SID of our database and ebs_patch is additional service_name which is required by online patching tool.
If you look at tnsnames.ora file in the Application tier $TNS_ADMIN directory you will find below kind of entry:
<SID>_patch= (DESCRIPTION= (ADDRESS=(PROTOCOL=tcp)(HOST=<your_database_server_name>)(PORT=<your_database_port>)) (CONNECT_DATA= (SERVICE_NAME=ebs_patch) (INSTANCE_NAME=<your_database_SID>) ) )
During patching phase, adop will use this tns entry to connect to database.
• Invokes the TXK script $AD_TOP/patch/115/bin/txkADOPPreparePhaseSynchronize.pl to synchronize the patches which have been applied to the run APPL_TOP, but not the patch APPL_TOP.
• Checks the database for the existence of a patch edition, and creates one if it does not find one.
+++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
2) APPLY PHASE DETAILS
In the apply phase, adop applies the specified patches to the system. Patches are applied to the patch edition of the database and file system.
How to execute:
Example:
$ adop phase=apply patches=1234,7891 workers=8
Where 1234 and 7891 are the patch numbers
What it will do:
If a post-installation patch step mentions any tasks that need to be performed explicitly, where they are run from depends on the type of patching:
• In a normal online patching cycle, the steps should be executed from the patch file system after the apply phase.
• If the patch is being applied in hotpatch mode or downtime mode, the steps should be executed from the run file system after the apply phase.
+++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
3) FINALIZE PHASE DETAILS
The finalize phase will be executed while the application is still online. It is used to perform any remaining processing that is needed to ensure the system is ready for the fastest possible cutover.
Used to perform the final patching operations that can
How to execute:
$ adop phase=finalize
What it will do:
• Pre-compute DDL that needs to be run at cutover.
• Compile all invalid objects.
• Validate that the system is ready for cutover.
If finalize_mode=full, compute statistics for key data dictionary tables for improved
performance.
VERY IMPORTANT 1 : Up to this phase, you can run a special phase called abort, which will undo the changes made so far in the patching cycle. After cutover is complete, however, you cannot do this.
VERY IMPORTANT 2 : In an online patching cycle, the requisite JAR files are initially stored in the $APPL_TOP/admin/<SID>/out directory, and then uploaded into the database during the cutover phase. Therefore, the out directory must not be deleted at least until cutover (next phase) is complete.
+++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
4) CUTOVER PHASE DETAILS
Used to perform the transition to the patched environment. Shuts down application tier services, makes the patch edition the new run edition, and then restarts application tier services. This is the only phase the involves a brief downtime.
Important: No users should remain on the system during cutover, as there will be a short downtime period while the application tier services are restarted. Also, any third-party processes connected to the
old run edition of the database should be shut down, or they will be terminated automatically.
How to execute:
$ adop phase=cutover
What it will do:
• Shut down internal concurrent manager. The adop utility signals the internal concurrent manager to shut down, but will wait for any existing concurrent requests to finish before it proceeds with cutover actions.
Note: Cutover will take longer if it has to wait for long-running concurrent processes to complete. In such a case, you can expect to see an informational message of the form: [STATEMENT] [END 2013/10/28 23:47:16] Waiting for ICM to go downIf you do not want to wait for in-progress concurrent requests to finish normally, you can terminate the internal concurrent manager by executing the adcmctl.sh abort command from a different shell.
• Shut down application tier services: All application tier services are brought down. During this period, the system is unavailable to users.
• Cutover database: Promote patch database edition to become the new run database edition, using adzdpmgr.pl script.
• Cutover file system: Promote patch file system to become the new run file system, switching the $FILE_EDITION values in the patch and run enviroments. The current patch APPL_TOP becomes the new run APPL_TOP, and the current run APPL_TOP becomes the new patch APPL_TOP. Terminate old database sessions: Terminate any database connections to the old run edition of the database.
• Start application tier services: Application tier services are restarted, on the new run edition. The system is now available again to users
• ADZDPATCH concurrent program is cancelled when the cutover phase is complete.
+++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
5) CLEANUP PHASE DETAILS
Important: If you fail to run the cleanup phase explicitly, it will be run automatically on the next prepare cycle, but this will cause a delay in starting your next online patching cycle.
This adop phase is used to remove obsolete code and data from old editions.
How to execute:
$ adop phase=cleanup
What it will do:
• Various actions are performed during cleanup, including dropping (removing) obsolete: Crossedition triggers, Seed data, Editioned code objects (covered objects), Indexes, Columns, Editions.
Using parameter cleanup_mode:
a) cleanup_mode=quick – Performs minimum cleanup, including removal of obsolete crossedition triggers and seed data.
Use quick cleanup when you need to start the next patching cycle as soon as possible. For example, if you want to start a new patching cycle right away, but have not yet run cleanup from the previous patching cycle, you can use quick cleanup mode to complete the essential cleanup tasks as fast as possible.
b) cleanup_mode=standard – Does the same as quick mode, and also drops (removes) obsolete editioned code objects (covered objects).
This is the default mode , so does not need to be specified.
c) cleanup_mode=full – Performs maximum cleanup, which drops all obsolete code and data from earlier editions
Use full cleanup when you want to recover the maximum amount of space in the database. If you have run a large number of patching cycles, or applied a very large patch such as a rollup, significant space may be consumed by obsolete table columns and recovered by running a full cleanup. A full cleanup should only be performed when there is no immediate need to start a new patching cycle.
+++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
THERE ARE TWO SPECIAL PHASES:
A) ABORT PHASE DETAILS
Abort PHASE is conditional phase. This phase cannot be specified with any other phase.
If for some reason either the prepare or apply phase failed or gave problems, you can abort the patching cycle at either of these points by running a special phase with the Command. The actions taken will be discarded (rollbacked).
IMPORTANT: This abort command is only available up to (but not including) the cutover phase. After cutover, the system is running on the new edition, and abort is no longer possible for that patching cycle.
How to execute:
The command to perform this operation is:
$ adop phase=abort
What it will do:
• Confirms that there is an in-progress online patching cycle, so the abort call is therefore valid.
• Checks for the existence of a patch edition and drops one if it exists.
• Cancels the ADZDPATCH concurrent program, if it is running.
• Deletes the rows inserted for the pending session ID from the ad_adop_sessions and ad_adop_session_patches tables.
VERY IMPORTANT: After running abort, a full cleanup must be performed. The cleanup command is: adop phase=cleanup cleanup_mode=full). This will remove any columns that were added by the patch but are no longer needed because of the abort. If they are not removed, they may cause problems in a later patching cycle.
Alternatively, you can run a combined command to abort the patching cycle and perform a full cleanup:
$ adop phase=abort,cleanup cleanup_mode=full
If any attempt was made to apply patches to the patch edition, after abort you must run the fs_clone phase (adop phase=fs_clone) to recreate the patch file system.
+++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
B) FS_CLONE PHASE DETAILS
The fs_clone phase is a command (not related to adcfgclone.pl) that is used to synchronize the patch file system with the run file system. The fs_clone phase should only be run when mentioned as part of a specific documented procedure.
How to execute:
The fs_clone phase is run using the following command:
$ adop phase=fs_clone
What it will do:
This phase is useful if the APPL_TOPs have become very unsynchronized (meaning that there would be a large number of delta patches to apply). It is a heavyweight process, taking a backup of the entire current patch APPL_TOP and then cloning the run APPL_TOP to create a new patch APPL_TOP. As this method requires more time and disk space, it should only be used when the state of the patch file system is unknown. This command must be invoked from the run file system, before the next prepare phase is run.
Note: The patch file system requires at least 25 GB of free disk space to be available for adop operations, including fs_clone. If there is insufficient free space, the adop operation will fail.
If an fs_clone operation fails, you can rerun it with the option force=yes to restart it from the beginning (with the same session ID), or force=no to restart it from the point where it failed.
——————————————————————————————————————–
IMPORTANT POINTS REGARDING ONLINE PATCHING:
1. adop utility is put under $APPL_TOP_NE/ad/bin. It is a wrapper script which calls internally the perl script $AD_TOP/bin/adzdoptl.pl which does actual work of applying the patch.
2. adop will automatically set its environment as required, but it is the user’s responsibility to set the environment correctly for any other commands that may be run. Set the run edition environment whenever executing commands that you intend to affect the run edition.
For example:
$ . <EBS_ROOT>/EBSapps.env run $ adstrtal.sh
Set the patch edition environment whenever you intend to execute commands that affect the patch edition.
For example:
$ . <EBS_ROOT>/EBSapps.env patch $ sqlplus apps/apps @my_custom_patch_script.sql
3. All the phases need to be completed and you can’t skip any of these. For example, if you try to skip prepare phase, you may get error message like “Apply phase can only be run while in a patching cycle, i.e. after prepare phase.”
4. After an online patching cycle is started, you should not perform any configuration changes in the run edition file system. Any that are made will not be propagated and will therefore be lost after cutover is complete.
5. You should not attempt to clone an Oracle E-Business Suite system while an online patching cycle is in progress.
6. The prepare, apply, and fs_clone phases all require at least 10GB of free disk space. All other phases require 1GB of free space. A warning message will be displayed if less than the needed amount is available.
7. The directories where you extracted the patches applied in a given patching cycle must be retained, in the same location and with the same contents, until the next prepare phase completes. This is also a requirement for patches applied in a hotpatch session.
8. Maintenance Mode is not needed for online patching, and so Maintenance Mode is not available in Oracle E-Business Suite Release 12.2.
——————————————————————————————————————-
ADOP ON MULTI-NODE
In a multi-node environment, one application tier node will be designated as the primary node. This is the node where the Admin Server is located, and will usually also be the node that runs Oracle HTTP Server. All other application tier nodes are designated as secondary nodes.
adop commands are invoked by a user on the primary node. Internally, adop uses Secure Shell (ssh) to automatically execute required patching actions on all secondary nodes. You must set up passwordless ssh connectivity from the primary node to all secondary nodes.
If a node unexpectedly becomes inaccessible via ssh, it will be abandoned by adop, and the appropriate further actions taken. Consider a scenario where the adop phase=prepare command is run in a system with ten application tier nodes. The command is successful on nine nodes, but fails on the tenth. In such a case, adop will identify the services enabled on nodes 1-9. If they are sufficient for Oracle E-Business Suite to continue to run normally, adop will mark node 10 as abandoned and then proceed with its patching actions. If they are not sufficient, adop will proceed no further.
——————————————————————————————————————–
- Oracle Multitenant DB 4 : Parameters/SGA/PGA management in CDB-PDB - July 18, 2020
- Details of running concurrent requests in Oracle EBS - May 26, 2020
- Oracle Multitenant DB 3 : Data Dictionary Architecture in CDB-PDB - March 20, 2020
Very well explained in simplified manner. Nice to read your every blog.
Great Post and nicely explained . Everything is very well Documented and also available for download 🙂 Keep it up .
what are the objects covered/created in patch edition. is it only the objects which are getting patched or all the code objects in database stored in patch edition?
pl answer it.
I just want to say thankyou so much.Your Post is really very veryyyyy…… helpful.
Please keep going on posting.May god bless you.
Excellent …
Thanks Brijesh…
Nice document
Very clear explanation. Thanks.
I wonder if you can provide me with any clarification regarding the development access to the instance at any point of the Online Patching process. The consensus in my team is we should not touch the database objects during any of the online patching stages, even though the users may access the application. If so it will significantly impact our development access to the instance. Maybe after all we can keep working in “patch” partition, can we?
Good Post Brijesh
All the Topics are excellent in the Blog,Very Usefull
Excellent article and very helpful Brijesh Sir.
Very Good and article Brijesh..
Excellent document
Very helpful article . Thank You Brijesh.
Awesome….explanations… No word to say
Great exlanations..Keep posting all good stuff sir
Very Good Brijesh Sir
Thank you sir your blog was excellent and also very simple to understand
Superb blog…simple to understand….
Thank you sir…nice explanation and very nice document.
If it is possible please post the 12.2 interview questions.
Hi Sir,
Please tell me where we need to apply adop in patch file system or run file system?
Thanks in Advance
Sreenivas
Hi there,
Is there any documentation on how to create patch for custom oracle application?
Thanks in advance.
Regards
Niranjan
Very clear explanation about adop phases awesome knowledge sharing blog .
Thanks a lot Brijesh.
Regards
Nagarjuna
very nicely explained in great detail. thanks for this great post.
Excellent blog … Thank you so much
Hi Brijesh,
Thanks for sharing the info.
Can you pls let me know ,what are all the deployments we shouldn’t do once the adop patching cycle starts.
I know we shouldn’t do the file system level configurations but if we do the same level changes in patch file system also I do not think its an issue.
and also if any deployments like .sql,.pkgs.,rtfs,LDT ..etc kind of deployments can we do in the progress of ADOP ?I think yes but want to make sure .
Mainly what kind of deployments we shouldn’t do ,hope you got my question.
Thanks
Sardar
Awesome…. explanations!!!
excellent details bhai Sab
The post touches some unknow areas of ADOP. Well prepared.
I have one doubt::
Prior to cut-over phase, the fs1 has not patches applied.
fs2 was applied with bunch of patches. So fs2=fs1+patches.
At cutover the fs2 become run edition. After this phase, the fs1=fs2-patches.
What process synchronizes fs1 from fs2 to make fs1=fs2 ??
Can you please put some light on this?
I hope fs_clone is not the correct one.
Thank YOU
Hi Sundar ,
This is my understanding , it will synchronise again when you start next ADOP cycle of prepare using below script.
Invokes the TXK script $AD_TOP/patch/115/bin/txkADOPPreparePhaseSynchronize.pl to synchronize the patches which have been applied to the run APPL_TOP, but not the patch APPL_TOP.
Thanks,
Shailesh Kumar
This the absolutely useful! thank you!
Please share my_custom_patch_script.sql
Hi Sundar ,
This is my understanding , it will synchronise again when you start next ADOP cycle of prepare using below script.
Invokes the TXK script $AD_TOP/patch/115/bin/txkADOPPreparePhaseSynchronize.pl to synchronize the patches which have been applied to the run APPL_TOP, but not the patch APPL_TOP.
Thanks,
Shailesh Kumar